2021 Street Reconstruction Plans:
2021 Street Reconstruction Project – AL-2021-01
- Beaumont St- Greene Ave to E. Mission Rd +/- 2,100 ft
- Kalb Ave- Libal St to Termini +/- 950 ft
2021 Street Reconstruction Project – AL-2021-02
- Roselawn Blvd- Riverside Dr east +/- 1,400 ft
2021 Street Resurfacing Project – AL-2021-03
- St. Mary’s Blvd – Webster Ave west +/- 1,400 ft
- Rosemont Dr- Webster Ave to Arbor Lane +/- 1,425 ft
- Kalb Ave- Webster Ave to Libal St +/- 2,500 ft
Alternates:
- Hilltop Dr– Clay St to Delahaut St +/- 960 ft
- McCormick St– Clay St to S. Irwin Ave +/- 1,620 ft
- St. Joseph St Alley- +/- 150 ft
2021 Sanitary Sewer Lining Project – AL-2021-04
- St. Mary’s Blvd – Webster Ave west +/- 1,400 ft
- Roselawn Blvd – Riverside Dr east +/- 1,400 ft
- Sioux Ln – In easement between Sioux Ln and Beaumont St
2021 Sanitary Lateral Replacement Project – AL-2021-05
- St. Mary’s Blvd – Webster Ave west +/- 1,400 ft
- Green Isle Park
2021 Webster Avenue Sanitary and Storm Sewer Televising Project – AL-2021-07
- 25,000 Linear Feet of Sanitary and Storm Sewer
- 225 Sanitary Sewer Laterals